Cable ops
Cable operations in progress until 13 mar by cableship layla in area bound by 12-29N 055-14W, 13-17N…
Western North Atlantic · NAVAREA IV 235/22
- issued
- 2022-03-09 10:00Z
- status
- cancelled 2022-03-10 10:12Z (archive)
- cancels
- NAVAREA IV 223/22
- authority
- M/V LAYLA 090909Z MAR 22.
- position
- 12.959, -55.602
- source
- nga_json · first seen 2026-08-17 13:38Z
Original warning text
WESTERN NORTH ATLANTIC. 1. CABLE OPERATIONS IN PROGRESS UNTIL 13 MAR BY CABLESHIP LAYLA IN AREA BOUND BY 12-29N 055-14W, 13-17N 056-02W, 13-23N 055-52W, 12-32N 055-08W. ONE MILE BERTH REQUESTED. 2. CANCEL NAVAREA IV 223/22. 3. CANCEL THIS MSG 14 MAR 22.
This area · cable & pipeline work
14 within 180 nm since 2014 · 0 in the last 12 months · 0 in force now
14
15
20
22
- Cable operations by cableship layla: a. 121040Z to 121700Z mar in area bound by 12-29N 055-14W, 13-17N…2022-03-12
- Cable operations in progress until 18 mar by cableship layla in areas bound by: a. 12-29N 055-14W, 13-17N…2022-03-10
- Cable operations in progress until 10 mar by cableship layla in areas bound by: a. 15-04N 057-36W, 15-32N…2022-03-04
- Cable operations by cableship layla: a. 03 to 05 mar in area bound by 15-04N 057-36W, 15-32N 058-04W, 15-40N…2022-03-03
- Cable operations 22 feb until further notice by M/V lida in area bound by 14-03.40N 056-27.08W, 13-40.25N…2022-02-20
- Cable operations in progress until further notice by M/V layla in areas within six miles of trackline…2022-01-23
Season · when cable & pipeline work happen here
J
F
M
A
M
J
J
A
S
O
N
D
month of issue, all years in the archive
Timeline
- Cable operations in progress until 10 mar by cableship layla in areas bound by: a. 15-04N 057-36W, 15-32N…cancels · 2022-03-04
- Cable operations in progress until 10 mar by cableship layla in areas bound by: a. 15-04N 057-36W, 15-32N…replaced · 2022-03-04
- Cable operations in progress until 18 mar by cableship layla in areas bound by: a. 12-29N 055-14W, 13-17N…cancelled by · 2022-03-10
Nearby now · within 120 nm
Nothing else in force within 120 nm.
Worldwide now
35 cable & pipeline work in force · see all
Cable ops
Cable laying, pipeline and seismic operations. All current cable & pipeline work →
Not for navigation. This is a re-rendering of an official navigational warning for awareness; mariners must use official NAVAREA broadcasts and their national MSI service.